Braintree Demolition Permit Guide
Coverage: Braintree. Each line links to the official page it comes from; the source list gives each page’s own date where it shows one, and the date it was checked.
Who issues the permit, and how to apply
- Braintree’s demolition permit covers only the complete demolition of a structure, not selective demolition of portions of buildings. — Braintree Building Division
- Braintree takes building permit applications through online permitting and no longer accepts paper applications. — Braintree Building Division
Before demolition starts
- A Braintree demolition application includes the Town of Braintree Demolition Sign-Off Form and the demolition contractor’s Massachusetts Construction Supervisor License. — Braintree Building Division
- If a one- or two-family dwelling is involved, the demolition contractor’s Home Improvement Contractor registration is attached. — Braintree Building Division
- The application also includes the contractor’s workers’ compensation affidavit and liability policy, and a signed contract between the contractor and the property owner. — Braintree Building Division
Asbestos
- Braintree’s DPW says friable asbestos should be removed and disposed of by an asbestos abatement professional. — Braintree DPW
- Massachusetts requires a written asbestos survey by a state-certified inspector before any demolition or renovation; MassDEP requires notice ten working days ahead for asbestos work, and for construction or demolition projects except in residential buildings with fewer than 20 units. — MassDEP (Massachusetts rules that apply everywhere)
Historic review and demolition delay
- Braintree’s Demolition Delay ordinance (Chapter 5.700) applies to any building more than 75 years old, in whole or in part, or of unknown age, that meets one or more of its listed criteria. — Braintree Town Council
- For a building at least 75 years old, the Inspector of Buildings forwards the application to Planning, which notifies the Historical Commission chair. — Braintree Town Council
- As amended in 2026, the Commission chair, vice-chair and the Director of Planning and Community Development make the initial significance determination. — Braintree Town Council
- If the initial determination is positive, the Commission holds a public hearing within 35 days and mails notice to owners of property within 300 feet of the lot. — Braintree Town Council
- If the Commission finds a significant building preferably preserved, a demolition permit may not issue until four months after that determination, and a vacant building must be secured to the Inspector of Buildings’ satisfaction. — Braintree Town Council
- The chapter does not apply to buildings in a designated M.G.L. c. 40C historic district or to landmarks certified under M.G.L. c. 40, § 8D. — Braintree Town Council
- The Town Council passed the amended ordinance on October 20, 2026; the order shows mayoral approval dated October 22, 2026. — Braintree Town Council
Debris and waste-ban rules
- Braintree states that construction and demolition bulky waste is not picked up curbside, and defines C&D to include windows, doors, flooring, roof materials, fencing, pallets and toilets — any non-household trash item. — Town of Braintree
- Construction and demolition material cannot be accepted at the drop-off center. — Town of Braintree
Fees, with the date the town gives
- Braintree’s building fee schedule effective July 1, 2026 has no separate demolition line, and charges double the permit fee for work begun without a permit. — Braintree Building Division
Points to confirm before filing
Braintree’s online permitting notice says applicants no longer need signatures from other departments when submitting, while the Time Saving Information sheet still lists the Demolition Sign-Off Form. Ask the Building Division which applies. — Braintree Building Division, Braintree Building Division
Statewide guides
Massachusetts Asbestos & Demolition Notifications · Massachusetts Construction Debris Disposal Bans · Where construction debris can legally go: facilities south of Boston
Other towns
Demolition Permit Guides for Boston, Quincy and the South Shore · Interior Demolition in Braintree
Any scope of work that requires a state license is performed by licensed specialists that D. Clancy & Sons coordinates as part of the project.
Sources
- Braintree Building Division — Time Saving Information for Applicants (checked November 8, 2026)
- Braintree Building Division — Online permitting notice (checked November 8, 2026)
- Braintree DPW — Asbestos (checked November 8, 2026)
- MassDEP — Asbestos, Construction & Demolition Notifications (checked November 8, 2026)
- Braintree Town Council — Order 26-026: Demolition Delay Ordinance amendment (Chapter 5.700) (dated October 22, 2026; checked November 8, 2026)
- Town of Braintree — Construction & Bulky Waste (checked November 8, 2026)
- Town of Braintree — Drop-Off Center Services (checked November 8, 2026)
- Braintree Building Division — Building fee schedule (effective July 1, 2026) (dated July 1, 2026; checked November 8, 2026)
More guides
- All demolition regulation guides
- Demolition Permit Guides for Boston, Quincy and the South Shore
- Massachusetts Asbestos & Demolition Notifications
- Massachusetts Construction Debris Disposal Bans
- South Shore Transfer Station Debris Rules
- Boston Dumpster Permits
- Boston Site Cleanliness License, Explained
- Boston vs. Quincy Demolition Permits
- Where construction debris can legally go: facilities south of Boston