Boston, in Suffolk County, and Quincy, in Norfolk County, run different demolition-permit regimes. Boston puts a Landmarks Commission review — Article 85 (Boston Landmarks Commission) — ahead of the demolition permit; Quincy’s Inspectional Services checklist is built around utility sign-offs and site conditions. This page puts the two side by side, with every rule linked to the city that publishes it. Other cities and towns in Suffolk and Norfolk County have their own requirements; the authority for each is that municipality’s building department.
| Boston (Suffolk County) | Quincy (Norfolk County) | |
|---|---|---|
| Authority | Boston Landmarks Commission for Article 85; Inspectional Services for the demolition permit. — Boston Landmarks Commission, Boston Inspectional Services | Inspectional Services, Building Department. — City of Quincy Inspectional Services |
| What triggers it | Before demolishing a building in Boston you must submit an Article 85 application. Scope: all buildings in Downtown or Harborpark, and all other buildings at least 50 years of age. — Boston Landmarks Commission | This checklist governs a building permit to perform demolition activities. — City of Quincy Inspectional Services |
| Where to apply | Since May 23, 2022, only through the Boston Landmarks Commission online portal — no paper, no email. The signature page must be notarized. — Boston Landmarks Commission | Online through the city’s ViewPoint permitting system. — City of Quincy Inspectional Services |
| Review clock | Ten days of staff review from a complete application; a public hearing within forty days if the structure is found significant; no demolition permit until ninety days after the close of the hearing if demolition delay is invoked. — Boston Landmarks Commission | The checklist does not state a review period. Ask Inspectional Services, Building Department. — City of Quincy Inspectional Services |
| Utilities | Shut-off notices from underground and overhead utilities: gas, electrical, telephone, cable. — Boston Inspectional Services | A natural gas utility letter stating when service was terminated at the street; an electric utility letter stating the same. — City of Quincy Inspectional Services |
| Water and sewer | A closed Boston Water and Sewer Commission general service agreement. — Boston Inspectional Services | Quincy Water Billing Office approval that the water meter was removed by City personnel; Quincy Sewer/Drain Department approval that service was terminated at the street. — City of Quincy Inspectional Services |
| Dig Safe and street work | A Dig Safe reference number. — Boston Inspectional Services | A Dig Safe letter or number; a street opening / trench permit from the Engineering Department. Street work may only be performed by approved contractors. — City of Quincy Inspectional Services |
| Hazardous materials | MassDEP approval for hazardous materials. — Boston Inspectional Services | Not among the checklist items listed on this page. Ask Inspectional Services, Building Department. — City of Quincy Inspectional Services |
| Site conditions | Not among the Inspectional Services items listed on this page. Ask Inspectional Services. — Boston Inspectional Services | A hydrant meter for dust control, or an invoice for a water truck. Rodent bait boxes every 40 feet of site perimeter, inspected bi-weekly. — City of Quincy Inspectional Services |
Also required for the demolition permit: shut-off notices from underground and overhead utilities (gas, electrical, telephone, cable); a closed Boston Water and Sewer Commission general service agreement; MassDEP approval for hazardous materials; and a Dig Safe reference number. — Boston Inspectional Services
This checklist governs a building permit to perform demolition activities. — City of Quincy Inspectional Services
Any scope of work that requires a state license is performed by licensed specialists that D. Clancy & Sons coordinates as part of the project.