Family-Owned Since 1975Serving Boston & the South Shore
Guide

Boston Dumpster Permits

Scope: the City of Boston only. Other cities and towns set their own dumpster rules, and none of them is covered here — the authority for each is that municipality’s own departments. Prices below are national figures published by Angi, not Boston figures.

What a dumpster costs

D. Clancy & Sons quotes each job individually. The figures on this page are ranges published by the named sources, not a quote.

  • Dumpster rental: $294–$480 per week, by size and rental lengthAngi
  • 2-cubic-yard dumpster, about 400 lb: $75–$200 per weekAngi
  • 40-yard roll-off, 5–6 tons: up to $800 per weekAngi
  • Weight overage fees: up to $200Angi
  • Angi's guidance: construction materials, yard waste and hazardous items need different handling, which affects the total. — Angi

What Boston requires to place one

  • A permit is required to have a dumpster. — Boston Public Works
  • A dumpster needs a license from Public Works only if it sits on a public way; that license is obtained through a street occupancy permit. — Boston Inspectional Services
  • The Site Cleanliness Ordinance applies to every bulk refuse container, commercial or residential. — Boston Inspectional Services
  • The Site Cleanliness License fee is $50. Boston Inspectional Services
  • A home with six or more units needs a Site Cleanliness Permit from Inspectional Services (City Ordinance Article 23, Section 2); the fine is $50, and not more than $1,000. — Boston Public Works
  • City property may not be occupied without valid permits from Public Works and Inspectional Services (Article 16, Section 122A). — Boston Public Works
  • Dumpsters may not be overfilled (Article 23, Sections 1 and 8); the fine is $50. — Boston Public Works

What the street occupancy application asks

  • For containers, the applicant supplies a letter of authorization from the company that owns them, and that company must hold a bond with the City. — Boston Public Works
  • Surety bond: $5,000 for occupancy permits, $20,000 for excavation permits. — Boston Public Works
  • The application asks whether a chute or other drop method is used; what staging or fencing is used; whether the sidewalk is obstructed and whether an ADA-compliant pedestrian detour is provided; the length of the truck; and how much street length and width will be used. — Boston Public Works
  • Blocking metered spaces: signs at least two days before the job, fliers at least one day before. — Boston Public Works
  • Public Works may withhold a permit if the scope of work is insufficiently described. — Boston Public Works

Questions to put to Boston Public Works

  • Is a chute or other drop method being used? — ask Boston Public Works (Boston Public Works)
  • What staging or fencing is used? — ask Boston Public Works (Boston Public Works)
  • Is the sidewalk obstructed, and is an ADA-compliant pedestrian detour provided? — ask Boston Public Works (Boston Public Works)
  • What is the length of the truck? — ask Boston Public Works (Boston Public Works)
  • How much street length and width will be used? — ask Boston Public Works (Boston Public Works)
  • Are metered spaces being blocked, and have signs gone up at least two days before and fliers at least one day before? — ask Boston Public Works (Boston Public Works)

Boston vs. Quincy Demolition Permits

Any scope of work that requires a state license is performed by licensed specialists that D. Clancy & Sons coordinates as part of the project.

Sources

  1. Boston Inspectional ServicesHow to apply for a Site Cleanliness License
  2. Boston Public WorksHow to get a street occupancy, excavation or driveway permit