Who issues the permit, and how to apply

Before demolition starts

  • Hanover’s noise bylaw allows construction and demolition equipment in Residential Districts from 7:00 a.m. to 7:00 p.m. on weekdays and 8:00 a.m. to 7:00 p.m. on other days. — Town of Hanover

Asbestos

  • The transfer station prohibits asbestos materials of any kind or content, including floor tiles, siding, boilers and roofing shingles the operator suspects contain asbestos. — Hanover DPW
  • Massachusetts requires a written asbestos survey by a state-certified inspector before any demolition or renovation; MassDEP requires notice ten working days ahead for asbestos work, and for construction or demolition projects except in residential buildings with fewer than 20 units. — MassDEP (Massachusetts rules that apply everywhere)

Historic review and demolition delay

  • Under bylaw 6-26, a demolition permit for a building that is in whole or in part 75 years old or more may not issue without following the bylaw’s procedure; a building of unknown age is assumed to be over 75. — Town of Hanover
  • The applicant files with the Building Inspector, who forwards a copy to the Historical Commission within seven days when the bylaw applies; the Commission decides within thirty days whether the building is significant. — Town of Hanover
  • If the building is found significant, the Commission holds a public hearing, and abutters are notified in writing at least five business days beforehand. — Town of Hanover
  • If the Commission finds a building preferably preserved, a demolition permit may not issue within twelve months of notification unless the Commission agrees otherwise. — Town of Hanover
  • The Building Inspector may issue an emergency demolition permit when the Inspector, Fire Chief or Board of Health Agent finds an immediate threat to public health or safety. — Town of Hanover
  • After a demolition without a permit, a building permit may not issue on the parcel for three years, except for a faithful restoration or as the Commission agrees. — Town of Hanover

Debris and waste-ban rules

  • The noise bylaw has dumpsters emptied between 6:00 a.m. and 8:00 p.m. on weekdays and 7:00 a.m. to 8:00 p.m. on other days. — Town of Hanover
  • Hanover’s transfer station rules allow residential waste only; vehicles with commercial plates must attest they will dispose only of waste from their own Hanover household. — Hanover DPW
  • Clean-outs of materials from rental units by a landlord are considered commercial waste and are not accepted at the station. — Hanover DPW

Fees, with the date the town gives

  • Hanover’s building permit fee schedule effective July 1, 2025 sets $15.00 per thousand based on construction, with no separate demolition line; minimums are $100.00 for commercial/industrial and $50.00 for one- and two-family work, and work without a permit is charged a double fee. — Hanover Building Department
  • An owner who demolishes without a permit under bylaw 6-26 (bylaws as amended through May 2026) faces a fine of not more than $300, each day a separate offense. — Town of Hanover

Statewide guides

Massachusetts Asbestos & Demolition Notifications · Massachusetts Construction Debris Disposal Bans · Where construction debris can legally go: facilities south of Boston

Other towns

Demolition Permit Guides for Boston, Quincy and the South Shore

Any scope of work that requires a state license is performed by licensed specialists that D. Clancy & Sons coordinates as part of the project.

Sources

  1. Hanover Building and Inspectional Services — Building and Inspectional Services (checked November 8, 2026)
  2. Town of Hanover — General Bylaws, as amended through the May 2026 Annual Town Meeting (dated August 31, 2026; checked November 8, 2026)
  3. Hanover DPW — Transfer Station Rules & Regulations (April 2025) (dated April 18, 2025; checked November 8, 2026)
  4. MassDEP — Asbestos, Construction & Demolition Notifications (checked November 8, 2026)
  5. Hanover Building Department — Building permit fees (effective July 1, 2025) (dated July 1, 2025; checked November 8, 2026)