Norwell Demolition Permit Guide
Coverage: Norwell. Each line links to the official page it comes from; the source list gives each page’s own date where it shows one, and the date it was checked.
Who issues the permit, and how to apply
- Norwell’s bylaw defines the demolition permit as the permit the Building Official issues under the State Building Code for demolition, partial demolition or removal of a building. — Town of Norwell Zoning Bylaw (eCode360)
- Norwell requires building, plumbing and electrical permits for work on existing structures, and its Building Department notes that the state building code requires licenses from builders, remodelers, electricians, plumbers and other trades. — Norwell Building Department
- A copy of license, a certificate of liability insurance, contracts and floor plans accompany a building permit application. — Norwell Building Department
Before demolition starts
- A Norwell demolition permit application must give the building’s address and age, whether it is on the inventory or the National Register, a brief description of the project and proposed future use, and photographs of what is to be demolished. — Town of Norwell Zoning Bylaw (eCode360)
Asbestos
- Massachusetts requires a written asbestos survey by a state-certified inspector before any demolition or renovation; MassDEP requires notice ten working days ahead for asbestos work, and for construction or demolition projects except in residential buildings with fewer than 20 units. — MassDEP (Massachusetts rules that apply everywhere)
Historic review and demolition delay
- Under the demolition delay bylaw, demolition means razing a building or a significant portion of one, excluding ordinary repairs or maintenance as determined by the Building Official. — Town of Norwell Zoning Bylaw (eCode360)
- Under Norwell’s demolition delay bylaw, a building built before 1925, or of unknown age, counts as significant, as do buildings on the town’s inventory or the National Register. — Town of Norwell Zoning Bylaw (eCode360)
- A demolition permit may not issue until the Building Official determines whether the building is a Significant Building; for one that is, the application goes to the Historical Commission within seven days. — Town of Norwell Zoning Bylaw (eCode360)
- The Commission, or an authorized Designated Member, makes a written determination within 10 business days of the Building Official forwarding the application; otherwise it has 30 more days to open and hold a public hearing. — Town of Norwell Zoning Bylaw (eCode360)
- Notice of the hearing goes to the applicant, the owners of all adjoining properties, the Building Official, the Planning Board and the Select Board. — Town of Norwell Zoning Bylaw (eCode360)
- If the Commission finds a Significant Building preferably preserved, the demolition permit may not issue for 12 months from the determination unless the Commission agrees otherwise. — Town of Norwell Zoning Bylaw (eCode360)
- A finding that a Significant Building is not preferably preserved stays in effect for 10 years, unless a later application has a greater or different scope. — Town of Norwell Zoning Bylaw (eCode360)
- After a non-compliant demolition, a building permit may not issue for the parcel for three years, though the Commission may waive or modify that. — Town of Norwell Zoning Bylaw (eCode360)
Debris and waste-ban rules
- The Norwell Recycling Center is for Norwell residents only, and no commercial businesses or vehicles are allowed. — Town of Norwell
- Norwell’s state waste ban page lists construction material and debris, including wood, asphalt, brick, concrete and sheetrock, as banned from disposal in Massachusetts. — Town of Norwell
Fees, with the date the town gives
- Norwell’s fee schedule revised August 27, 2024 lists residential demolition at $10.00 per $1,000.00 of project valuation, $50.00 minimum and commercial demolition at $15.00 per $1,000.00 of project valuation, $100.00 minimum; applying after the work is done costs double. — Norwell Building Department
- Demolishing a Significant Building without complying with the bylaw (as amended May 5, 2025) carries a fine of not less than $300 per violation, which the Commission may issue. — Town of Norwell Zoning Bylaw (eCode360)
Points to confirm before filing
Norwell’s bylaw gives the Commission 10 business days to decide in one clause, while another lets the Building Official issue the permit if no determination is made within the seven-day period. Confirm the current window with the Building Official. — Town of Norwell Zoning Bylaw (eCode360)
Statewide guides
Massachusetts Asbestos & Demolition Notifications · Massachusetts Construction Debris Disposal Bans · Where construction debris can legally go: facilities south of Boston
Other towns
Demolition Permit Guides for Boston, Quincy and the South Shore
Any scope of work that requires a state license is performed by licensed specialists that D. Clancy & Sons coordinates as part of the project.
Sources
- Town of Norwell Zoning Bylaw (eCode360) — Article 15: Building Demolition Delay (checked November 8, 2026)
- Norwell Building Department — Building Department (checked November 8, 2026)
- Norwell Building Department — Permitting & Fees (checked November 8, 2026)
- MassDEP — Asbestos, Construction & Demolition Notifications (checked November 8, 2026)
- Town of Norwell — Recycling Center (checked November 8, 2026)
- Town of Norwell — State Waste Ban Materials (checked November 8, 2026)
- Norwell Building Department — Permit fee schedule (revised August 27, 2024) (dated August 27, 2024; checked November 8, 2026)
More guides
- All demolition regulation guides
- Demolition Permit Guides for Boston, Quincy and the South Shore
- Massachusetts Asbestos & Demolition Notifications
- Massachusetts Construction Debris Disposal Bans
- South Shore Transfer Station Debris Rules
- Boston Dumpster Permits
- Boston Site Cleanliness License, Explained
- Boston vs. Quincy Demolition Permits
- Where construction debris can legally go: facilities south of Boston